Streets adjacent to McKinney’s new city hall, which is under construction, are expected to be reconstructed in the year prior to the opening of the new municipal facility, according to a Dec. 5 council meeting.
McKinney City Council members unanimously approved awarding a construction contract for the reconstruction of parts of Virginia Street and Throckmorton Street at the meeting.
A closer look
The project will include three phases of construction on the streets directly south and east of the new city hall site.
The phases include:
- 1. Constructing Throckmorton Street from Lamar Street to just north of the intersection with East Virginia Street
- 2. Constructing East Virginia Street from SH 5 to Main Street
- 3. Constructing a roundabout at the intersection of East Virginia Street and Throckmorton Street